Progress of monitoring of CHPP construction in Sovetskaya Gavan
Currently, on the CHPP construction site in the City of Sovetskaya Gavan, works are underway for construction of foundations for the main building of the CHPP. CJSC SSE experts monitor the progress of works and control payments in the process of the project implementation until the CHPP commissioning.
Works are performed under the agreement for technical and price auditing and monitoring CHPP construction progress, entered into between OJSC Sberbank of Russia and CJSC SWECO SOYUZ Engineering in November, 2013.
Commissioning of the CHPP in the City of Sovetskaya Gavan with the installed electric capacity of 126 MW and heat capacity of 200 Gcal/h will allow to replace the exhausted capacity resource of the existing Mayskaya GRES, and ensure reliable heat supply to the city.