Scope of Work:

  • Project description and assessment of adequacy of initial permits and design estimates;
  • Analysis of the current work progress;
  • Engineering supervision over the Project implementation;
  • Financial supervision over the Project implementation;

Bank

VTB Bank

Customer

Eco Energy Rus LLC

Location

Narimanovsky district, Astrakhan region, Russia

Services

Construction Audit

Term of The Contract

2018–2019