Pre-FEED for Pulp Mill construction in Krasnoyarsk Territory

Scope of Work:

  • Selection of optimum capacity and expert review of the Lesosibirsk woodworking plant No.1 site to demonstrate that the Pulp Mill can be sited thereat.
  • Development of Specification for Supply of Main Process Equipment
  • Development of a feasibility study for the plant construction at the selected site
  • Public hearings basing on the deliverables – HVAV Volume (jointly with the Customer)
  • Preparation of Terms of Reference for Work as General Designer and General Contractor
  • The Project also includes development of several design options for the Cellulose Plant evaporation train with a 0.5 to 1.0 MTPA capacity.

Customer

Segezha Group

Location

Russia

Term of The Contract

2018–2019